PILOT SITE LISBON WITH MORE PV POWER PLANTS

What: Additional solar modules installed in Lisbon pilot site

Where: Lisbon, Portugal

When: January 2022

From the mid-January COMPILE pilot site Lisbon, led by our partner Coopernico, is richer for additional PV power plants. New solar modules were installed on the rooftop of the condominium and they are already producing the energy, for now still in individual self-consumption mode.

28 modules of 354 Wp were installed which means 9,66 kWp additional capacity. New PVs are supported by one inverter of 8 kWn. The whole pilot site has now a total capacity of 27,96 kWp.

Investment of 15.000 € (+23 % VAT) was provided by the condominium tenants, while the whole process, in terms of legal, regulatory and technical requirements, has been supported by Coopernico.

The Coopernico team is now working on shifting the pilot site from the individual self-consumption mode toward a collective self-consumption, including every tenant in this initiative.